Clinton Wind Farm

Client: Noble Constructors, LLC
Location: Chateaugay, New York
Year Started: 2007
Duration: 11 weeks

Major Scope and Features:

  • 80,885 Lineal Feet of Access Roads to 67 wind tower generators
  • Access roads owned by the Town and County were constructed 12’ wide with 14” crusher run base and installation of Geogrid to each tower.
  • 23.5 acres of clearing and grubbing
  • 2,318 Lineal Feet of hedge row stone wall removal.
  • Entire project Storm Water Pollution Prevention Plan (SWPPP) installation compliance and maintenance. 
  • Fast paced schedule; project was completed in five (5) weeks.